# Plans: timelines for your rooms

> Turn a room into a plan to schedule its desks on a timeline. See every plan's progress, finish date and warnings on the Plans page, and open one to plan it.

Source: https://plexiidesk.com/help/plans-overview
Section: Focus and flow > Tasks and plans
Plans: All plans
Updated: 2026-10-15

A plan is a room with a schedule. Make any room a plan and its desks, and the tasks filed on them, become the plan's tasks: you can lay them out on a timeline, link the ones that depend on each other, mark milestones and see what is running late. The **Plans** page lists every plan with its progress and finish date, so you can see at a glance which ones need you.

Nothing in a plan is a copy. A task in a plan is the same task you see on its desk and in All Tasks, and the schedule is worked out from the real dates, lengths and links you give it.

> **Note:**
> The **Plans** page is not the same as the plans you can buy (Free, Pro and Team). For those, see [Plans and pricing: Free, Pro and Team](https://plexiidesk.com/help/plans-and-pricing).

## Before you start

- Plans are available on every plan.
- **What counts as a plan's tasks:** every desk inside the plan's room, including desks in rooms inside it, and every task filed on those desks. Archived desks and desks in Trash are left out.
- **A plan shows on the Plans page once it has at least one task.** A plan you have just created opens straight away so you can add its first task.

## Open the Plans page

Any of these opens it:

- Press `⌘` `K` on a Mac (`Ctrl` `K` on Windows) and choose **Plans**. See [The command palette](https://plexiidesk.com/help/command-palette).
- Click **Plan** in the Home dashboard's **Quick actions** widget. See [Quick actions widget](https://plexiidesk.com/help/home-widget-quick-actions).
- Open the PlexiDesk app menu and choose **Plans**. See [Desk, Office, People and Brain: the four areas](https://plexiidesk.com/help/plexii-areas).
- Click a **Plans** shortcut in the **Shortcuts** widget. See [Shortcuts widget](https://plexiidesk.com/help/home-widget-shortcuts).

## Make a plan

### Turn an existing room into a plan

1. Open **All rooms**.
2. Point at the room's card and click **Make this a plan**, or right-click the card and choose **Make this a plan**.
3. The card now says **Plan**, and the room joins the Plans page (once it has a desk in it).

See [Create and organise rooms](https://plexiidesk.com/help/room-create).

### Start a new plan

1. On the Plans page, click **New plan** at the top right. You can also press `⌘` `K` (`Ctrl` `K` on Windows) and choose **New plan** from anywhere.
2. PlexiDesk creates a plan called **New plan** and opens it.
3. Click **Add task**, type the first task's title and press `Enter`. Each task you add here is created as a desk in the plan's room.

To rename the plan, go to **All rooms**, right-click its card and choose **Rename room**.

## What the Plans page shows

The page is titled **Plans**. Along the top, four totals cover all your plans:

| Total | What it counts |
| --- | --- |
| **Plans** | How many plans you have. |
| **Tasks done** | Finished tasks out of all the tasks in all your plans, such as **14/40**. |
| **Avg complete** | The average of each plan's percentage complete. |
| **At risk** | How many plans carry a **Drift** or **Cycle** warning. |

Under the totals is a card for each plan, in alphabetical order. Each card shows:

- **The plan's name.**
- **Drift**, in amber, when a task finished later than planned and is now pushing later work back. See [Baselines, working days, levelling and export](https://plexiidesk.com/help/plans-schedule-tools).
- **Cycle**, in red, when tasks depend on each other in a loop, so the plan cannot be scheduled properly. See [Edit a plan task and its dependencies](https://plexiidesk.com/help/plans-task-details).
- **How many tasks are done** out of the total, with the percentage and a progress bar.
- **Finishes** and the date the plan's last task is scheduled to end.

A plan's percentage is the share of its tasks that are finished. The **Progress** you set on a task's details does not change it.

If you have no plans yet, the page says **No plans yet.**

## Open a plan

1. Click the plan's card.
2. The plan opens on its **Overview**. The buttons at the top switch between **Overview**, **Timeline**, **Board**, **Grid**, **Calendar**, **Workload** and **Files**. See [Plan views: Overview, Board, Grid, Calendar, Workload and Files](https://plexiidesk.com/help/plans-views).
3. To go back to all your plans, click **Plans** at the top left.

## Make a plan an ordinary room again

1. Open **All rooms**.
2. Point at the plan's card and click **Remove from Plans**, or right-click the card and choose it.

The room leaves the Plans page. Its desks and their tasks stay where they are, with their due dates and other details.

## Good ways to use plans

- **A client project.** Keep one room per client project, make it a plan, and give each desk a planned finish. The timeline shows the order of work, and the critical path shows what cannot slip.
- **A launch.** Mark the launch day and key reviews as milestones, link the work that leads up to them, and check **Running late** on the Overview each morning.
- **A weekly check.** Look at the **At risk** total on the Plans page and open any plan with a **Drift** or **Cycle** warning.

## Common questions

### My plan is not on the Plans page

A plan appears once it has at least one task that is not archived or in Trash. Open the room, add a desk, and the plan appears. A plan that is archived, or in Trash, is not listed either.

### I opened the plan from All rooms and did not see a timeline

Opening a plan from **All rooms** opens its dashboard page. The timeline and the other planning views are on the Plans page: open **Plans** and click the plan's card.

### Does making a room a plan change its desks?

No. The desks stay in the room and work as before. The plan adds a schedule on top of them.

### How do I delete a plan?

A plan is a room, so delete it the way you delete a room: in **All rooms**, right-click its card and choose **Move to Trash**. Its desks go with it. See [Archive, trash and restore rooms and desks](https://plexiidesk.com/help/desk-archive-trash).

## Related tasks

- [Use the plan timeline](https://plexiidesk.com/help/plans-timeline)
- [Plan views: Overview, Board, Grid, Calendar, Workload and Files](https://plexiidesk.com/help/plans-views)
- [Edit a plan task and its dependencies](https://plexiidesk.com/help/plans-task-details)
- [Baselines, working days, levelling and export](https://plexiidesk.com/help/plans-schedule-tools)
- [Create and organise rooms](https://plexiidesk.com/help/room-create)
- [Tasks, desks and subtasks](https://plexiidesk.com/help/tasks-overview)