A plan is a room with a schedule: make any room a plan and its desks, and the tasks filed on them, become the plan's tasks. You lay them out on a timeline, link the ones that depend on each other, mark milestones and see what is running late. Nothing is a copy, so a plan's task is the same task you see on its desk and in Focus.

What you can do
Timeline and critical path
See each task as a bar on the calendar, with dependency arrows, the critical path in red and a line for today; drag a bar to move it.
Seven views
Switch between Overview, Timeline, Board, Grid, Calendar, Workload and Files, and a change in one view shows in all of them.
Dependencies with lag
Link tasks finish to start, start to start, finish to finish or start to finish, with a lag in working days for a gap or an overlap.
Milestones and deadlines
Tick Milestone for an event such as a launch, and set a deadline so any task scheduled to finish after it is flagged in red.
Baselines and levelling
Set a baseline to track how tasks move, choose working days and holidays, and use Level so one person's tasks never overlap.
Export the plan
Click Export to save an XML project file that other project-planning apps can open, with tasks, links, costs and assignees.
How it fits your desk
Each desk in a plan's room is one of the plan's tasks, and Add task on a plan creates a new desk in that room. A task's Planned finish is its due date in Focus and the Desks app too.
Questions
Does making a room a plan change its desks?
No, the desks stay in the room and work as before. The plan adds a schedule on top of them.
Can I track costs in a plan?
Yes, give a task a cost and the Grid adds them up in a Total row. Costs have no currency, so use the same one throughout a plan.
Can I export a plan to another planning app?
Yes. Export saves an .xml project file with each task's dates, length, progress, milestones, deadlines, costs, links and assignees.
Why is my plan not on the Plans page?
A plan appears once it has at least one task that is not archived or in Trash. Add a desk to its room and it shows.